Skip to main content

Overview

Procurement in COMS is built around the Purchase Request (PR). A PR is the hub: everything else in a buy — the items you need, the bidders you invite, the RFQ/RFP you send them, the quotes that come back, the approvals, and finally the Purchase Order — hangs off it.

This chapter has four pages. Start here for the shape of the process, then go to the page that matches what you're doing:

Where to find it

In the left sidebar: Procurement → Purchase Requests. That opens the procurement workspace, which is a set of tabs over the whole module:

TabWhat it lists
OverviewDashboard of counts and charts for the period you pick. Only visible to people with the “view all” procurement permission.
Purchase RequestsEvery PR you're allowed to see. This is the main working list.
Purchase OrdersPOs, including those raised from a PR.
All SSJsSingle Source Justifications across all PRs.
All RFXsEvery RFQ/RFP/RFI document across all PRs.
Quotes & ProposalsEvery bid across all PRs — useful for “what has this vendor quoted us lately?”

The Procurement Overview tab. Note the banner about currency — see the warning below.

The Procurement Overview tab. Note the banner about currency — see the warning below.

⚠️ Heads up: Totals on the Overview tab are summed without currency conversion. If some bids or POs are in USD and others in CAD, the numbers are added together as raw figures. COMS says so on the page itself (“Amounts shown are estimates”). Treat them as rough indicators, not reportable financials. The same caveat applies to the Amount column and the “Amount (Low → High)” sort wherever bids are listed.

The life of a Purchase Request

A PR moves through four stages. The gauge at the top of every PR shows where it is:

StageWhat it meansWhat you can still change
PR CreatedThe PR exists. You're building it up — items, bidders, RFQ, quotes.Everything.
Bid SelectedYou've marked one bid as the winner.Most things. But the PR can no longer be deleted, and bid item costs are frozen for every bidder on the PR.
Ready For PurchaseYou've declared the PR complete and handed it to procurement to buy.Nothing. The PR and everything under it is locked.
PO CreatedA Purchase Order has been raised from the PR.Nothing.

If an approval on the PR is rejected, the gauge drops back and shows REJECTED in red.

The progress gauge, Suggested Next Steps, the Bidder List approval track, and the selected bid.

The progress gauge, Suggested Next Steps, the Bidder List approval track, and the selected bid.

Suggested Next Steps

COMS works out what the PR needs next and offers it as clickable chips in the dark panel at the top. You don't have to follow them, but they're the quickest route through, and they disappear one by one as you complete them. In order, they are:

ChipAppears when
Add itemsThe PR has no items yet.
Add biddersThe PR has no bidders yet.
Add SSJA non-competitive PR has bidders but no Single Source Justification.
Request bidder list approvalBidders are added but not yet sent for approval.
Request SSJ approvalAn SSJ exists but hasn't been sent for approval.
Generate/upload RFQ/P & send to biddersA bidder has no quoted items yet and there's no RFX for them.
Upload quotes & update bid item costsThe RFX has gone out but the costs aren't in yet.
Select winning bidEvery bidder has quoted and no winner is chosen.
Mark as ready for purchaseThere's a selected bid, the bidder list is approved, and (for non-competitive PRs) the SSJ is approved.

ℹ️ Good to know: The Mark as ready for purchase chip is the one that tells you the PR has cleared everything it needs. If it hasn't appeared, something upstream is still outstanding — check the Bidder List and SSJ tracks in the hero.

Two approval tracks

Separately from the main stage, a PR carries up to two approval chains, each with its own little progress bar in the hero:

TrackApplies toStates
Bidder ListEvery PR.Bidder(s) Added → Pending Bidder List Approval → Bidder List Approved (or Rejected)
SSJNon-competitive PRs only.SSJ Added → Pending SSJ Approval → SSJ Approved (or Rejected)

⚠️ Heads up: Once the Bidder List or the SSJ reaches Approved, the bidder list is frozen: you can no longer add, edit or remove bidders on that PR. Get the list right before you send it for approval. (Details: When bidder details freeze.)

Both tracks run through COMS's general Approvals module — see the Approvals chapter of this book for how requesting and deciding works.

Who can do what

Access is by role. The short version: procurement staff and managers see everything; everyone else sees the PRs they're connected to.

RoleCan seeCan createCan editCan delete
procurement-managerAll PRsYesAny PRYes
procurement-staffAll PRsYesAny PRNo
system-adminAll PRsAny PRNo
finance-staffAll PRs (read-only)NoNoNo
program-manager / project-manager / program-area-managerPRs in their own scopeYesIn their scopeNo
admin-assistantPRs in their own scopeYesIn their scopeNo
staff (any Conexus staff member)PRs they're connected toYesPRs they raisedNo
vendor-bidder (external supplier)Only their own quotes, on the external portalNoTheir own unlocked quoteNo

ℹ️ Good to know: “PRs they're connected to” means: you raised it, or you manage its program, program area or project, or you've recorded an approval decision on it. Any Conexus staff member can open Procurement and raise a PR — they just won't see other people's PRs unless one of those connections applies.

super-admin bypasses all of the above. A few hard data-integrity guards still bind even super-admin though — a locked PR can't be deleted by anyone, and neither can its bids or RFXs.

What's different from BMS

If you know the BMS procurement process, the flow will feel familiar. These are the real differences:

TopicIn COMS
Suppliers upload their own quotesThis is the big one. In BMS you received a quote by email and typed the numbers in yourself. In COMS the supplier gets a one-time link, enters their own line-item costs, and submits. Their quote then locks. See Quote locking and unlocking.
Bid comparisonThere is no heatmap or comparison chart in COMS yet. To compare, sort the Bidders tab by “Amount (Low → High)”, or use the module-wide Quotes & Proposals tab.
Suggested Next StepsNew in COMS. The PR tells you what it still needs instead of you remembering the order.
RFX typesRFQ and RFP can be generated from a template, same as BMS. RFI can be uploaded and recorded but has no generator template — if you generate one it comes out on the RFP template.
NotesEvery PR has a Notes tab with per-note visibility (everyone / just me / selected staff). Notes are an audit record: editable for 24 hours, then permanent.
PR numbersFormat YY.NNN (e.g. 26.075), and PRs and POs draw from the same number pool for the fiscal year. A PR converted to a PO keeps its number.
DocumentsBid files uploaded in BMS still show up, marked from BMS and view-only. See Documents on a bid.