Module 1 - Main Guide for Procurement (8 Lessons) Scenario 1
For a new project initiate the identification and approval of potential bidders (sole source justification (SSJ) or competitive bid)
Prepare for Supplier Non-Disclosure Agreements
Get Supplier sign NDA off (if required)
Create the initial RFX requirements and addressed clarifications
Notify Suppliers to prepare and submit bids for evaluation
Get Member/s approval of Supplier proposal/bid response & to purchase
Secure internal financial approvals and determine if member financing is approved for project
Initiate PO/IN generation and issue
Initiate the Supplier Score Card Process in parallel to the completion of the work (PO)
A project initiated in BMS requires the identification and approval of potential bidders (sole source justification (SSJ) or competitive bid). This is a gateway in from the Line of Business (LoB) processes.
The initiator needs to check to ensure that a valid NDA is in please before you start to engage the supplier/s with an RFX. (Reference COG-PR-PRO-007). The Procurement Manager (or delegate) needs to lead the negotiations to close the exceptions with the supplier until the supplier/Conexus have reached a mutually accepted version of the NDA.
RFX package is created/approved/reviewed.
Evaluation of bid response/s leading to Member/s approval.
Member/s approval of supplier proposal/bid response & to purchase - Gateway back into the LoB processes. Secure internal financial approvals and determine if member financing is approved for project.
PO/IN generation and issue of PO to supplier. Work is underway with the vendor and it's time to complete the quarterly vendor score card.
No comments to display